Horizontal Directional Drilling (HDD) work continues at Pacific City, Oregon, in preparation for the OOI cable installation. Over 3,500 feet of HDD conduit have been drilled to date, along what will be the path for the southern OOI cable (Segment 1). Another 1,500 feet to go before work can start on the alignment of the Northern cable segment. The weather is “somewhat” cooperating, and we are making good progress.